LARIMER COUNTY – The Colorado Department of Transportation and Kiewit Infrastructure Co. will open US 34 for travel between Loveland and County Road 43 (Drake) for access to Estes Park during the holiday season.
US 34 west of Drake remains closed for a two-mile stretch, so motorists on US 34 will use Larimer County Road 43 to travel between Loveland to Estes Park. Through travelers are still encouraged to use US 36 into Estes Park to avoid delays.
US 34 will open to all motorists (with or without residential permits) at 4 p.m. Friday, Dec. 22, and will remain open until 8:30 a.m. Tuesday, Jan. 2. Construction activities are ongoing and many areas continue to have only one passable lane, so pilot cars will navigate motorists through the canyon during the holiday opening. These lane restrictions and the anticipated extra traffic on the road for the holidays could mean delays exceeding one hour, especially on Sunday, Dec. 31. Motorists should plan for extra travel time if they plan to use US 34, and cyclists should plan not to ride in the busy one-lane corridor, for their safety. US 34 west of Drake remains closed for a two mile stretch, so motorists on US 34 will use Larimer County Road 43 to travel between Loveland to Estes Park. We encourage those drivers who can, to still use the US 36 and CO 66 detour for travel between Estes Park and Loveland.
This holiday opening is part of CDOT’s promise to reduce the inconvenience to canyon residents and nearby communities as much as possible. Drivers should remember to drive slowly and be prepared to stop at the single-lane sections.
During this scheduled opening, motorists will notice significant changes in the canyon since October:
-
Work between mile points 80 to 83 is nearly complete and we anticipate having two lanes open through this area when the highway opens for holiday travel. Inside this tight area, crews completed 14,000 cubic yards of soil-cement mixing; a process that combines natural material with cement to create a 15-foot section of man-made bedrock beneath the road surface. This mixture will create an extra level of resiliency through the narrows, by ensuring that the river cannot remove the roadway from below. Crews also installed all new drainage in this area. Short lane closures will be needed to complete minor work through May 2018.
-
From mile points 74 to 79, crews are still concentrating efforts on installing flood protection measures to the river banks and beneath the roadway.
-
At mile point 78, motorists will drive under a new highway bridge that will eventually carry vehicles above the Big Thompson River. Crews spent most of the summer months constructing these bridges which are scheduled to be complete in May 2018.
-
At mile point 77.5, motorists will drive over a new highway alignment which is placed on bedrock that was uncovered by the blasting work last winter.
-
Mile points 72 to 74, west of Drake, will remain closed where crews are repairing the highway near the landslide. The roadway will be protected with the installation of large boulders, cemented together, under the road.
-
Work will begin between mile points 70 to 72 in January. Residents should plan for delays when traveling to and from Estes Park.
“The project team has put in a lot of work over the first three months of the closure, and it’s exciting to see areas start to reopen. There is still a lot of work to be done, but we are committed to reopening the canyon just prior to Memorial Day, said Project Director James Usher.”
Following the holiday season, the highway will close again until just before Memorial Day 2018. To travel between Estes Park and Loveland drivers should use the detour on US 36 and CO 66. The only access on US 34 will be for canyon residents and emergency services through a permit process. The US 34 Big Thompson Canyon will reopen to the public just prior to Memorial Day.
When the canyon opens to regular traffic in May, drivers will see mostly clear roads, but there will still be some intermittent traffic delays similar to what drivers experienced in the summer of 2017. These lane closures will allow crews to complete paving and river work by the end of 2018.
US 34 Big Thompson Canyon’s roads and bridges were heavily damaged during the 2013 floods with many homes damaged and over 100 air lifted evacuations. The canyon and its residents also suffered from flooding in 1976. As a result of these two events CDOT has been studying the hydraulic flow of the river in the canyon and its impact on the road and bridges along its path while looking for safety improvements and resiliency solutions to prevent/protect against future flood event
CDOT PROJECT INFORMATION: For updates to this project, the public may call (970) 667-1005 or visit us34canyon.codot.gov. To sign up for “CDOT Alerts” on projects in your chosen area, visit CDOT’s website at www.codot.gov and choose the envelope icon at the bottom of the page. Or, to see CDOT’s lane closure reports for projects statewide, visit www.codot.gov/travel/
Support Northern Colorado Journalism
Show your support for North Forty News by helping us produce more content. It's a kind and simple gesture that will help us continue to bring more content to you.
BONUS - Donors get a link in their receipt to sign up for our once-per-week instant text messaging alert. Get your e-copy of North Forty News the moment it is released!
Click to Donate